Projects completed

Construction and assembly of the steel structure of the roof over the air handling units and the external roofing

ZUS building in Częstochowa

Investor: WIKTOR Company

Timeline: 05/2019 – 08/2019

Location: Częstochowa

Scope of works:

For the WIKTOR company, we carried out a task consisting of the construction and installation of a steel structure of a roof over the air handling units and external roofing as part of an investment task consisting of the demolition of the existing Building ‘D’, construction of a new office building and partial reconstruction of Building ‘B’ in the ZUS Branch in Częstochowa on Dąbrowskiego 43/45.